This resolution approves an amended agreement with CSXT Transportation, Inc. for preliminary engineering work related to the Frazier Street/Swinburne Bridge Replacement Project. The amendment increases the payment amount by $12,760, bringing the total not to exceed $32,780, with 95% of the costs reimbursable.
Resolution providing for an amended agreement with CSXT Transportation, Inc. for Preliminary Engineering work on the Frazier Street/Swinburne Bridge Replacement Project; and providing for the payment of the costs thereof, not to exceed Thirty-Two Thousand Seven Hundred Eighty Dollars ($32,780.00), an increase of Twelve Thousand Seven Hundred Sixty Dollars ($12,760.00) from the previously executed agreement, reimbursable at 95%.
What it does
- 1Amends agreement with CSXT Transportation, Inc. for preliminary engineering work on the Frazier Street/Swinburne Bridge Replacement Project
- 2Increases payment amount by $12,760 to a total not exceeding $32,780
- 3Costs are reimbursable at 95%
This resolution approves an amended agreement with CSXT Transportation, Inc. for preliminary engineering work related to the Frazier Street/Swinburne Bridge Replacement Project. The amendment increases the payment amount by $12,760, bringing the total not to exceed $32,780, with 95% of the costs reimbursable.
Activity timeline
- Status changedImpact 50
2026-0825: Mayor's Office for Signature → Passed Finally
- Status changedImpact 30
2026-0825: Reported from Standing Committee → Mayor's Office for Signature
- Status changedImpact 30
2026-0825: In Standing Committee → Reported from Standing Committee
Legislative history
Get alerts when 2026-0825 changes
LegisGo tracks every amendment, substitute, and vote on Metro Council legislation. Free to sign up. Alerts are instant or in a daily digest.
No credit card. Nashville Metro Council coverage is free during launch.